Project Description
Izmir Metro Project II Procurement and Implementation Support

Client : EBRD
Timeline: February 2019 – August 2021
Project Details
The EBRD finances the project of extending the existing metro line from Fahrettin Altay to Narlıdere. The project is 7.2 km long and consists of 2 tunnels and 7 stations.
Within the scope of this project, GREEN supports İzmir Metropolitan Municipality on:
- Preparation of construction tender documents,
- Control the construction tender according to EBRD rules,
- Submitting the reports requested by the EBRD from the Izmir Metropolitan Municipality in a timely manner,
- Project management, timely actions necessary to determine and mitigate risks,
- Support on environmental and social issues,
- Preparation of progress payments and payments in accordance with the contract.